November 26 - 30

Demolition, demolition, demolition!!!!  Currently Constructors, Inc. is working on Texas Avenue from 3rd street-Roselawn Avenue.  This area will be split into two pieces, both north and south sides, with the north side currently under demolition.  This entire construction area is estimated to take six weeks for overall construction completion. Please see the traffic flow map for business accessibility.  If you have any questions or concerns please contact Stephanie at MainStreet, 746-1117. 

Project Timeline

2nd and Texas - A work in progress! Click to see a larger picture.
May 2
May 17
May 24
May 30
July 10
July 20
July 27
Aug. 6
Aug. 6
Sept. 4
Sept. 4
Sept. 10
Sept. 10
Sept. 17
Sept. 26
Oct. 8
Oct. 18
Oct. 29
Nov. 5
Nov. 13
Nov. 26

 

 